Chapter 3 – The Project Management Process Groups
True / False
1. Decisions and actions taken in one knowledge area at a certain time rarely affect other knowledge areas.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: Project management is an integrative endeavor; decisions and actions taken in one knowledge area at a certain time usually affect other knowledge areas.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.86
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.15 – LO: 3-1
NATIONAL STANDARDS: United States – BUSPROG: Analytic
TOPICS: Project Management Process Groups
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/27/2018 3:49 PM
DATE MODIFIED: 5/17/2018 10:37 AM
2. Initiating processes take place during each phase of a project.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p. 87
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.15 – LO: 3-1
NATIONAL STANDARDS: United States – BUSPROG: Analytic
TOPICS: Project Management Process Groups
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/27/2018 3:49 PM
DATE MODIFIED: 4/27/2018 3:49 PM
3. Initiating processes are not required to end a project.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: Initiating processes are also required to end a project. Someone must initiate activities to ensure that the project team completes all the work, documents lessons learned, assigns project resources, and that the customer accepts the work.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.87
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.15 – LO: 3-1
NATIONAL STANDARDS: United States – BUSPROG: Analytic
TOPICS: Project Management Process Groups
KEYWORDS: Bloom’s:Comprehension
DATE CREATED: 4/27/2018 3:49 PM
DATE MODIFIED: 4/27/2018 3:49 PM
4. The level of activity and length of each process group varies for every project.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: The level of activity and length of each process group varies for every project. Normally, executing tasks requires the most resources and time, followed by planning tasks.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.88
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.15 – LO: 3-1
NATIONAL STANDARDS: United States – BUSPROG: Analytic
TOPICS: Project Management Process Groups
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/27/2018 3:49 PM
DATE MODIFIED: 4/27/2018 3:49 PM
5. Initiating and closing tasks are usually the longest and require the most amount of resources and time.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: Initiating and closing tasks are usually the shortest (at the beginning and end of a project or phase, respectively), and they require the least resources and time.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.88
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.15 – LO: 3-1
NATIONAL STANDARDS: United States – BUSPROG: Analytic
TOPICS: Project Management Process Groups
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/27/2018 3:49 PM
DATE MODIFIED: 4/27/2018 3:49 PM