Test Bank For Modern Systems Analysis And Design 6th Edition By Jeffry E.Hoofer
Chapter 3 Managing the Information Systems Project
1) The project manager is responsible for initiating, planning, executing, and closing down the project.
Answer: TRUE
Diff: 1 Page Ref: 47
2) The focus of project management is to assure that systems development projects meet customer expectations and are delivered within budget and time constraints.
Answer: TRUE
Diff: 2 Page Ref: 47
3) A deliverable is an end product in a phase of the SDLC.
Answer: TRUE
Diff: 1 Page Ref: 48
4) A resource analysis plan determines if the proposed information system makes sense for the organization from an economic and operational standpoint.
Answer: FALSE
Diff: 2 Page Ref: 49
5) A systems development project may be undertaken to take advantage of business opportunities or to solve business problems.
Answer: TRUE
Diff: 2 Page Ref: 49
6) In order to determine the resources required for project completion, an organization should analyze the project’s scope and determine the project’s probability of successful completion.
Answer: TRUE
Diff: 2 Page Ref: 49
7) The most instrumental person to the successful completion of a project is the database analyst.
Answer: FALSE
Diff: 2 Page Ref: 50
8) Project planning is the first phase of the project management process in which activities are performed to assess the size, scope, and complexity of the project and to establish procedures to support later project activities.
Answer: FALSE
Diff: 2 Page Ref: 51
9) When a project manager is getting projects completed through the effective utilization of resources, he/she is performing a risk and change management activity.
Answer: FALSE
Diff: 3 Page Ref: 51
10) When a project manager works closely with customers to assure project deliverables meet expectations, he/she is performing a customer relations activity.
Answer: TRUE
Diff: 2 Page Ref: 51